Central Waterfront Transmission Line Relocation Project Fieldwork Continues This Weekend-April 20 and 21

This Saturday, April 20 and Sunday, April 21, crews will continue investigative fieldwork for Phase 2 of the Central Waterfront Transmission Line Relocation Project. Utility location (potholing) activities will occur inside and outside of the Seattle Tunnel Partners (STP) fenced-off work zone.

Federal Sustainability Expert to Deliver Keynote Address at Powerful Business Energy Conference

Sustainability expert Judith Heerwagen from the office of Federal High Performance Green Buildings at the US General Services Administration will be the morning keynote speaker at the Electric League of the Pacific Northwest’s 2013 Powerful Business Energy Conference to be held May 23 at the Meydenbauer Center in Bellevue.

Seattle City Light Dispatchers Oversee Large Operation, Still Provide Personal Service

At the center of Seattle City Light’s operations is a team of 24 dispatchers at Seattle City Light’s System Control Center, who often work one-on-one with customers in times of need.

Power Restored to Customers in University District and Capitol Hill

Seattle City Light Crews have restored power to all customers in the University District and Capitol Hill Neighborhoods that lost power due to a lightning strike damaging equipment at the University Substation. There are still isolated power outages associated with this evenings lightning and crews hope to have power restored… [ Keep reading ]

Nearly 15,000 Without Power in University District and Capitol Hill

Seattle City Light Crews are working diligently to restore power to about 10,000 customers affected by an outage in the University District, Capitol Hill neighborhoods. The outage was caused by an equipment failure at the University substation. Estimated time of restoration is 1:00 am. For precise outage boundaries, visit our… [ Keep reading ]

Central Waterfront Transmission Line Relocation Fieldwork Continues This Weekend-April 13 and 14

This Saturday, April 13 and Sunday, April 14, crews will continue investigative fieldwork for Phase 2 of the Central Waterfront Transmission Line Relocation Project. This includes potholing activities inside and outside of the Seattle Tunnel Partners (STP) fenced-off work zone.

Call for Partners for Innovative Neighborhood Solar Program

Local non-profit Northwest Sustainable Energy for Economic Development (Northwest SEED) and Seattle City Light are seeking community partners for a new Solarize Washington campaign in central and southeast Seattle area neighborhoods.

City Light Employees to Volunteer for Earth Day at Duwamish Hill Preserve

In honor of Earth Day 2013, a team of 25 Seattle City Light employees and their family members will join hundreds of other volunteers at the Duwamish Alive event April 20.

City Light’s Jim Baggs Part of Next City Business Casual, April 11

Seattle City Light Interim Power Supply and Environmental Affairs Officer Jim Baggs will be one of the special guests when the Seattle Office of Economic Development’s City Business Casual networking program returns April 11 with a “What’s Next for Green Business” theme.

Central Waterfront Transmission Line Relocation Field Work Continues Sunday – April 7

This Sunday, April 7, crews will continue investigative fieldwork for Phase 2 of the Central Waterfront Transmission Line Relocation Project. The work is necessary to complete the design that will lead to the relocation of transmission lines off the Alaskan Way Viaduct before it is demolished.