Seattle City Light Completes Construction at 6th Avenue & Cherry Street

This past June, Seattle City Light recently completed the final stages of civil construction at 6th Avenue and Cherry Street. Crews excavated for new conduit (duct bank) between the existing electrical vaults on the west side of 6th Avenue and the south side of Cherry Street.

6th & Cherry Duct Bank Project Begins in September

In early September 2016, Seattle City Light plans to install a new conduit (duct bank) between the existing electrical vaults on 6th Avenue and Cherry Street. Crews plan to excavate on the west side of 6th Avenue into the south side of Cherry Street. The new duct bank will be installed and the street restored. This project will allow us to provide new electrical connections in the area.

Electrical Upgrade: First Avenue Between Columbia and Cherry Streets

Seattle City Light will be by replacing electrical ducts and cable between Columbia and Cherry streets along First Avenue downtown.