City Light Completes Electrical Reliability Improvements at Summit Slope Park

This past December, Seattle City Light recently completed civil construction in parts of East John Street and Summit Avenue East, near Summit Slope Park. The project began in late September 2016 to increase the reliability of the electrical system in the Capitol Hill neighborhood.

City Light Plans Work to Increase Reliability on Summit Avenue East

Seattle City Light is working to increase the reliability of the electrical system in the Capitol Hill neighborhood by installing new conduit (duct bank) and electrical vaults along Summit Avenue East and East John Street. The work will be completed in three stages.