City Light Completes Infrastructure Investment at Webster Point

Seattle City Light and its contractor, KC Equipment, have completed the first phase of an electrical reliability and capacity upgrade in the Webster Point neighborhood of Laurelhurst.

Seattle City Light and its contractor have completed a major milestone in the utility’s plans to improve the capacity, technology, and reliability of the electrical system in the Webster Point neighborhood of Laurelhurst.

KC Equipment has recently completed the installation of underground conduits, vaults, and equipment in order to replace outdated 4kV (4,000 volt) electrical equipment with updated 26kV (26,000 volt) infrastructure. Sidewalks, driveways, planting strips, and street panels affected by the work have been restored. A map showing the construction area and representative during and after photos are shown below.

The current 4kV cable is buried directly in the ground. The high capacity 26 kV cable will be protected by the installed conduit and vaults for greater reliability. The new 26kV electrical system will also have more switching points resulting in shorter outages with fewer customers affected when maintenance is required.

The infrastructure phase of the project was started in March of 2015 and completed earlier in May, 2016. The higher-capacity 26kV cable will be pulled in at a later date. Seattle City Light appreciates the patience of its customers during the successful completion of this important part of the project.

WebsterPointnomargin2Capture

Webster Point Work Location

 

WP_20151009conduitshoring

Typical view during construction: Conduits under sidewalk

 

WP_20150921restoredsidewalk

Typical after: sidewalk restored

To learn more about Seattle City Light’s investments in infrastructure, visit our Construction Website.